Bomas Project Cost Rises to Sh45.1 Billion After Kenya Cancels Summa Contract and Reprices Deal for CRBC

NAIROBI, Kenya — The cost of redeveloping Bomas of Kenya has climbed to Sh45.1 billion after the government stripped the Turkish contractor Summa of the project and handed a repriced contract to CRBC, The Standard reported on November 16, 2026, in an accounting that adds to the burden taxpayers have carried from the cancellation of tenders.
The newspaper reported that ending Summa's engagement and transferring the works to CRBC at a renegotiated price pushed the project's total cost to Sh45.1 billion, a level above the value of the deal under which the Turkish firm had been hired. The repricing resets what the public pays for works scoped under the original agreement, and the adjustment has landed at Sh45.1 billion in total, leaving the state meeting a bigger bill for the same redevelopment.
The Standard cast the Bomas adjustment as the latest cost generated by procurement reversals, a category of expenditure that grows each time the government cancels a signed tender and must re-award the works at new prices. The cancellation in November 2024 of agreements linked to India's Adani Group covering the expansion of Jomo Kenyatta International Airport and new power transmission lines marked an earlier high-profile case in the same pattern.
Bomas of Kenya is a state-owned cultural and conference complex in Langata, on the south-western edge of Nairobi, where recreated traditional homesteads and daily performances have made it a fixture of the capital's tourism circuit. The state corporation that runs the site, Bomas of Kenya Limited, was established to preserve and showcase the cultures of the country's communities. Its main hall ranks among the largest auditoriums in Kenya and has served as the national tallying venue for general elections, including the announcement of presidential results in 2013, 2017 and 2022.
Summa, the Turkish construction firm removed from the job, had held the contract for the redevelopment until the state terminated the arrangement, a decision that cleared the way for the works to be re-issued to a replacement builder at the higher figure now attached to the project.
That builder, CRBC, is China Road and Bridge Corporation, a subsidiary of the state-owned Chinese group China Communications Construction Company. The firm delivered Kenya's Standard Gauge Railway between Mombasa and Nairobi, opened in May 2017 at a construction cost of about 3.8 billion US dollars, financed largely by the Export-Import Bank of China and described at the time as the country's biggest infrastructure undertaking since independence.
CRBC also built the Nairobi Expressway, the roughly 27-kilometre elevated toll road opened in 2022 and operated through its Moja Expressway unit under a public-private arrangement, giving the company one of the longest construction records of any foreign contractor working in Kenya.
The Standard's figures put the price of the Bomas redevelopment at Sh45.1 billion once the repricing for CRBC is counted, the newest quantified entry in the running cost the state has incurred from scrapping and re-issuing a major government tender.