Kenya Airways Could Launch Accra-Canada Flights if Ghana Airline Deal SucceedsUK Graduate Visa Under Threat as Reform UK Proposes Drastic Post-Study ChangesSponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homesMwakilishi News Bulletin - Midday Edition, Friday 27 November 202619 Dead in One Week: NCIC Calls for Restraint as Ethnic Clashes Escalate in Isiolo and GarissaSponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homesUS Visa Applicants to Lose $750 Priority Interview Option From January 2027Kenyan Woman Esther Nyaga Wins Alberta Premier's Public Service Award in CanadaSponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homesTrendingGreen Card Lottery Winner Beatrice Karanja Left Homeless in Pennsylvania, Appeals for HelpTrendingUSCIS Shortens U.S. Citizenship Routes for Spouses, Military Members and Children of AmericansSponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homesTrendingHumphrey Mararu: From a Kenyan High School Teacher to a Lieutenant Colonel in US ArmyTrendingKenyan Green Card Winner Reveals How Addiction Threatened Her ResidencySponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homesTrendingKenya Loses Sh450 Billion Annually to Road Crashes, Chirchir RevealsTrendingNairobi Airspace to Close on November 27, December 4 and 12 SponsoredUnity Homes — Eunice Kinyanjui — Meet & Greet in White Marsh, MD · Nov 25–Dec 4 · Tatu City homes
QR code: Mwakilishi app on Google PlayGet the Mwakilishi appFree on Google PlayKenya diaspora news on your phone, free on Google Play. Scan the code with your phone's camera to install.Get the app
AdvertisementTop banner · 970×90 / 728×90
Sports

Raila Odinga International Stadium Reaches 93% Completion Ahead of AFCON 2027

Raila Odinga International Stadium Reaches 93% Completion Ahead of AFCON 2027

The Raila Odinga International Stadium is now more than 93 percent complete, according to Sports Cabinet Secretary Salim Mvurya, who inspected the facility this week.

AdvertisementIn-article ad

The 60,000-seat stadium is being prepared as one of Kenya’s main venues for the 2027 Africa Cup of Nations, which the country will co-host with Uganda and Tanzania. Mvurya said the progress was substantial and that the government remained confident the project would be completed on time.

The main pitch has been installed, while several major systems have been tested. Giant LED screens, ring lighting and a modern sound system are already in place, with engineers continuing to work on finishing details.

Get the day’s top stories by email

The Mwakilishi Daily News Digest: Kenya and diaspora news, once a day. Free, and you can unsubscribe anytime.

The cost of the project has risen to about Sh45.8 billion. Mvurya defended the investment, saying Kenya needs modern facilities that can host football, cultural events and youth activities. He noted that the country had not built a stadium of this scale since Kasarani was completed in 1987.

The Confederation of African Football (CAF) has been involved in inspections and has recommended changes to some areas of the stadium, including the presidential pavilion. Mvurya said technical teams were preparing designs to meet CAF requirements, with the cost of the modifications to be established after the assessments.

Also read Kenya's 'World-Class' Stadium Nears Historic Inauguration as East Africa Counts Down to AFCON 2027

Security and spectator management systems are also being upgraded. Sixty of the planned 91 turnstiles have been installed, while work continues on the skyboxes, landscaping and external facilities.

Three training grounds within the wider complex are also at different stages of completion. Supporting infrastructure includes a dedicated power substation, feeder roads and a planned railway station intended to improve access for spectators.

The complex will also include a musical aquatic fountain and façade lighting. The government says the wider development is intended to provide facilities that can be used beyond the AFCON tournament.

Mvurya said the stadium could host its first matches as early as November or December, ahead of the tournament. He said staging matches before AFCON would allow organisers to test the facility and address any operational problems.

During his inspection of Talanta Stadium on 19 August, Mvurya said the venue was 94 percent complete, with only final works remaining. The government is also preparing a roadmap for Harambee Stars ahead of the tournament. Mvurya said the technical team had been tasked with developing a strategy to ensure Kenya’s national team is competitive and capable of challenging for the title.

The preparations include both major stadium projects and supporting infrastructure intended to ensure Kenya is ready to host the continental tournament and make use of the facilities after AFCON.

Comments

Comments are reviewed before they appear. By posting you agree to our comment rules: we have zero tolerance for abusive or objectionable content. Use Report on any comment that breaks them.

No comments yet — be the first.

AdvertisementMore stories (Google matched content)

More from Sports